Posts

চিন্তা

PLUMBING DESIGN REPORT​

March 12, 2026

এম মাহফুজ সরকার

21
View

PLUMBING DESIGN REPORT

Project No: PDR-2025-001

PLUMBING DESIGN REPORT

Mixed-Use Commercial and Residential Development

Project NameRiverfront Mixed-Use Tower
Project No.PDR-2025-001
Location123 Riverfront Avenue, Dhaka, Bangladesh
ClientRiverfront Properties Ltd.
Prepared ByM. Ahmed, PE | Civil & Environmental Engineer
DateMarch 2025
RevisionRev. 0 – For Construction
StandardsBNBC 2020 / IPC 2021 / ASHRAE

CONFIDENTIAL – FOR CONSTRUCTION USE ONLY

1. Executive Summary

This Plumbing Design Report has been prepared for the Riverfront Mixed-Use Tower, a 24-story development comprising commercial retail spaces on the ground and mezzanine floors and residential apartments on floors 3 through 24. The report presents the engineering basis, system design criteria, and technical specifications for all plumbing systems within the building.

The plumbing design encompasses potable cold and hot water supply, sanitary drainage, storm drainage, natural gas distribution, fire suppression interface, and specialty systems including a rainwater harvesting installation. All systems have been designed in compliance with the Bangladesh National Building Code (BNBC 2020), the International Plumbing Code (IPC 2021), and applicable ASHRAE standards.

SystemPeak DemandKey Standard
Cold Water Supply42 L/s (666 gpm)IPC 2021 / BNBC 2020
Hot Water Supply18 L/s (285 gpm)ASHRAE 90.1
Sanitary DrainageDN 150 main stackIPC 2021
Storm Drainage120 L/s design flowBNBC 2020
Natural Gas250 kPa supply pressureNFPA 54

2. Project Description

2.1 Building Overview

The Riverfront Mixed-Use Tower is a 24-story reinforced concrete structure with two basement levels. The building occupies a 2,400 m² footprint and provides approximately 52,000 m² of gross floor area. The lower four floors accommodate retail, restaurant, and commercial office tenants, while floors 5 through 24 contain 240 residential apartment units of varying configurations.

Floor LevelUseArea (m²)Occupancy
B2 – B1Parking & MEP Plant Rooms4,800Restricted
Ground FloorRetail & Lobby2,200A-2 / M
MezzanineRetail & Food Court2,000A-2
Floors 2 – 4Commercial Office6,600B
Floors 5 – 24Residential Apartments (240 units)39,000R-2
Roof LevelMEP Equipment, Water Tanks1,400Restricted

2.2 Applicable Codes and Standards

The plumbing systems have been designed in accordance with the following codes, standards, and references:

• Bangladesh National Building Code (BNBC) 2020

• International Plumbing Code (IPC) 2021

• International Mechanical Code (IMC) 2021

• ASHRAE Standard 90.1-2019: Energy Standard for Buildings

• ASHRAE Standard 55-2020: Thermal Environmental Conditions

• NFPA 54: National Fuel Gas Code

• NFPA 13: Standard for Installation of Sprinkler Systems (fire interface)

• WHO Guidelines for Drinking-Water Quality, 4th Edition

• Manufacturer specifications and installation guidelines

3. Water Supply System

3.1 Demand Calculations

Domestic water demand has been calculated using the fixture unit method per IPC 2021 Table 603.1, cross-referenced with BNBC 2020 occupancy-based consumption rates. Demands are tabulated below for each occupancy zone.

Occupancy ZoneFixture UnitsPeak Demand (L/s)Daily Usage (m³/day)
Residential (240 units)1,840 FU28.5312
Commercial Office420 FU6.874
Retail / Food Court380 FU5.256
Common Areas & BOH120 FU1.516
Total Building2,760 FU42.0458

3.2 Water Storage and Pressurization

The building utilizes a break-tank and booster pump strategy to ensure code-compliant pressures throughout all floors. Underground cisterns in Basement Level 2 provide emergency storage, while rooftop gravity tanks serve upper residential floors.

ComponentCapacity / RatingLocationQuantity
Underground Break Tank200 m³B2 Plant Room2
Rooftop Gravity Tank80 m³Roof Level2
Booster Pump Set (Low Zone)42 L/s @ 45 m headB1 Plant Room1 (1 standby)
Booster Pump Set (High Zone)28 L/s @ 90 m headB1 Plant Room1 (1 standby)
Pressure Reducing ValvesSet at 500 kPaEach Floor Riser24

3.3 Pipe Sizing and Materials

Cold water distribution mains are CPVC Schedule 80 or Type L copper for sizes DN 25 and below. Risers DN 50 and above are Schedule 40 galvanized steel with mechanical couplings. All underground runs are HDPE DR-11, thermally fused.

Pipe SectionMaterialSizeDesign Velocity (m/s)
Underground supply mainsHDPE DR-11DN 1501.2
Vertical risers – low zoneGalvanized Steel Sch. 40DN 1001.5
Vertical risers – high zoneGalvanized Steel Sch. 40DN 801.5
Branch mains (per floor)CPVC Sch. 80DN 501.0
Fixture connectionsType L CopperDN 15 – DN 250.8

4. Hot Water System

4.1 Hot Water Demand

Hot water demand is calculated at 45% of peak cold water fixture units per ASHRAE 90.1-2019 and BNBC 2020 residential standards. Design hot water delivery temperature is 60°C at the heater and 55°C at the most remote fixture to prevent Legionella growth, per WHO guidelines.

ZonePeak HW Demand (L/s)Storage Required (L)Recovery Rate (L/h)
Residential – Floors 5–148.212,0003,800
Residential – Floors 15–246.49,6003,200
Commercial / F&B3.45,0002,000
Total18.026,6009,000

4.2 Hot Water Plant

Hot water is generated by gas-fired storage water heaters with stainless steel inner tanks and polyurethane foam insulation. A dedicated hot water recirculation loop maintains delivery temperature within 2°C of set point throughout all occupied periods.

• Gas-fired water heaters: 4 × 250 L capacity, 90 kW input each

• Recirculation pump: 0.8 L/s at 30 kPa, with variable-speed drive

• Thermostatic mixing valves set at 50°C for residential fixtures

• Temperature and pressure relief valves per ANSI Z21.22

• Drain pans and floor drains beneath all storage units

5. Sanitary Drainage System

5.1 System Design Basis

The sanitary drainage system is designed as a single-stack soil-waste-vent system per IPC 2021, with separate venting provisions. The primary soil stack is DN 150 from basement to roof level, transitioning to DN 100 branches at each floor. All drainage is gravity-fed to the municipal sewer connection at Basement Level 2.

5.2 Drainage Fixture Units (DFU) Summary

Floor RangeTotal DFUStack Size RequiredVent Stack Size
Roof – Floor 20820 DFUDN 100DN 75
Floor 19 – Floor 101,640 DFUDN 125DN 100
Floor 9 – Floor 22,460 DFUDN 150DN 100
Ground – Basement3,100 DFUDN 200DN 125

5.3 Pipe Materials and Slope

All sanitary drain piping within the building is cast iron soil pipe (CISPI 301) with hub-and-spigot joints above slab and no-hub couplings in concealed locations. Underground building drains are PVC SDR 35. Minimum horizontal drain slope is 1:50 (2%) for DN 100 and larger; 1:40 (2.5%) for DN 75 and smaller.

• Stacks: Cast iron, hubless with neoprene gaskets

• Horizontal branches: Cast iron, minimum 2% slope

• Underground: PVC SDR 35, minimum 1% slope

• Grease interceptors: Commercial kitchen lines routed through 1,500 L grease trap prior to connection to building drain

• Floor drains: DN 100 P-trap with trap primer in mechanical and parking areas

6. Storm Drainage System

6.1 Rainfall Design Criteria

Storm drainage has been designed for the 25-year return period rainfall intensity applicable to Dhaka, Bangladesh, in accordance with BNBC 2020 Chapter 7. Design intensity is 125 mm/hr for roof drainage and 100 mm/hr for surface areas.

Drainage AreaArea (m²)Runoff Coeff.Design Flow (L/s)
Roof – Flat membrane2,4000.9579.2
Terraces / Podium Deck8000.8523.6
Surface Parking & Access1,2000.8026.7
Landscaped Areas4000.353.9
Total Design Flow4,800133.4

6.2 Roof Drainage

Roof drainage employs a primary gravity system with 100 mm cast iron roof drains at a maximum spacing of 20 m, connected to vertical DN 100 – DN 150 leaders routed inside the building core. Secondary overflow scuppers are provided at 150 mm above the roof membrane surface per IPC Section 1108.

• Primary drains: 8 no. × DN 100 roof drains at 20 m centres

• Overflow scuppers: Minimum 200 mm wide at parapet walls

• Vertical leaders: DN 150 cast iron to storm chamber

• Sump pump (B2): 2 × 45 L/s submersible pumps for below-grade drainage

6.3 Rainwater Harvesting

A rainwater harvesting system is incorporated to reduce potable water consumption for toilet flushing and irrigation. Collected rooftop runoff is filtered, stored, and UV-disinfected before distribution through a dedicated non-potable purple-pipe system.

ComponentSpecification
Collection area1,800 m² treated roof area
First-flush diverter1.5 L/m² diverter volume
Filtration100 micron cartridge + activated carbon
UV Disinfection30 mJ/cm² minimum dose
Storage tank60 m³ HDPE underground cistern
Annual savings estimate~8,200 m³/year (18% of total demand)

7. Natural Gas Distribution System

7.1 Gas Demand Calculations

Natural gas demand has been calculated in accordance with NFPA 54 and the gas utility requirements of Titas Gas Transmission and Distribution Company. All appliance ratings have been obtained from equipment schedules and manufacturer data sheets.

Appliance / ZoneQuantityInput (kW each)Total Load (kW)
Gas-fired water heaters490360
Kitchen ranges – F&B1218216
Commercial cook tops624144
Residential ranges24081,920
Gas boilers (backup)2120240
Total Connected Load2,880
Demand Factor Applied (0.45)1,296

7.2 Pipe Sizing and System Layout

The medium-pressure gas main (250 kPa) enters at Basement Level 2 via a utility meter station. Pressure is regulated to 1.75 kPa (low pressure) for distribution within the building via two-stage regulation. Gas piping is Schedule 40 black steel with welded joints, coated and wrapped underground.

• Service entry: DN 100 black steel, welded

• Building main riser: DN 80 black steel

• Residential branches: DN 25 – DN 32 black steel

• Commercial kitchen branches: DN 40 – DN 50 black steel

• Emergency shut-off valves: Seismically activated, at building entry and each floor

• Leak detection: Continuous gas monitoring in plant rooms and kitchens

8. Sustainability and Water Conservation

The plumbing design incorporates multiple water and energy conservation strategies targeting a 35% reduction in potable water consumption relative to a baseline building per LEED v4.1 prerequisites.

StrategyStandard BaselineDesign PerformanceSavings (%)
Low-flow WC (4.8 L/flush)6.0 L/flush4.8 L/flush20%
Low-flow showerheads9.5 L/min5.7 L/min40%
Sensor lavatory faucets8.3 L/min1.9 L/min77%
Rainwater harvestingPotable flushNon-potable flush18%
Hot water recirculationNo recircInsulated loop + VSD15% HW energy
Composite annual savings458 m³/day298 m³/day35%

9. Equipment Schedule

The following major plumbing equipment is incorporated in the design. Contractor shall verify all dimensions and utility requirements prior to procurement.

TagDescriptionCapacity / RatingLocationQty
CWT-1Underground Cold Water Cistern200 m³ eachB2 Plant Room2
RWT-1Rooftop Gravity Tank80 m³ eachRoof2
BP-1Booster Pump – Low Zone42 L/s @ 45 mB1 Plant Room2
BP-2Booster Pump – High Zone28 L/s @ 90 mB1 Plant Room2
HW-1Gas Storage Water Heater250 L / 90 kWB1 Plant Room4
HWR-1HW Recirculation Pump0.8 L/s / VSDB1 Plant Room2
GI-1Grease Interceptor1,500 LB11
RHT-1Rainwater Harvest Tank60 m³B21
UV-1UV Disinfection Unit30 mJ/cm²B1 Utility1
SP-1Sump Pump (B2)45 L/s, submersibleB2 Sump2
PRV-1Pressure Reducing ValveSet: 500 kPaEach floor riser24
MR-1Gas Meter & Regulator Set250 kPa → 1.75 kPaB2 Meter Room1

10. Testing, Commissioning, and Inspection

10.1 Pressure Testing Requirements

All plumbing systems shall be tested in accordance with IPC 2021 Chapter 3 and the requirements of the local authority. Testing shall be witnessed by the Engineer of Record and documented in commissioning reports.

SystemTest MediumTest PressureDurationAcceptance
Water supply – above groundWater1.5× working pressure min. 860 kPa30 minNo leaks or drops
Water supply – undergroundWater1,200 kPa2 hrsNo leaks or drops
Sanitary drain/waste/ventWater3 m head (fill stack)15 minNo visible leaks
Gas piping – low pressureAir / Nitrogen345 kPa30 minNo pressure drop
Gas piping – medium pressureAir / Nitrogen690 kPa60 minNo pressure drop
Storm drainageWaterFill roof drains15 minNo leaks / overflow

10.2 Commissioning Checklist

Prior to system handover, the following commissioning activities shall be completed, documented, and submitted to the owner:

• Flushing and disinfection of all potable water systems per AWWA C651

• Water quality testing: turbidity, pH, chlorine residual, coliform bacteria

• Booster pump performance verification: flow, pressure, and power draw

• PRV calibration and lockout at design set point

• Hot water temperature verification at furthest fixture (minimum 55°C)

• Recirculation loop balancing and pump curve verification

• Grease interceptor inspection and baseline grease sample

• Gas leak survey with calibrated combustible gas detector

• Emergency gas shut-off valve function test

• UV disinfection unit validation per NSF/ANSI 55

• Roof drain flow test and overflow scupper function check

• Sump pump level control and alarm test

• BMS integration: sensor readings confirmed against local gauges

11. Plumbing Drawing Schedule

Drawing No.TitleScaleRevision
PL-001Plumbing Legend, Notes and AbbreviationsN/ARev. 0
PL-100Site Plumbing – Water Service and Storm1:500Rev. 0
PL-101Basement B2 – Plumbing Plan1:100Rev. 0
PL-102Basement B1 – Plumbing & Mechanical Plan1:100Rev. 0
PL-103Ground Floor – Plumbing Plan1:100Rev. 0
PL-104Typical Residential Floor Plan (Floors 5–24)1:100Rev. 0
PL-200Cold Water Riser Diagram – Low ZoneN/ARev. 0
PL-201Cold Water Riser Diagram – High ZoneN/ARev. 0
PL-202Hot Water & Recirculation Riser DiagramN/ARev. 0
PL-300Sanitary Drainage Riser Diagram – TowerN/ARev. 0
PL-301Storm Drainage Riser and Roof PlanN/ARev. 0
PL-400Natural Gas Riser DiagramN/ARev. 0
PL-500Rainwater Harvesting SchematicN/ARev. 0
PL-600Plant Room – Water Storage & Booster1:50Rev. 0
PL-700Plumbing Details and SectionsVariousRev. 0

12. References and Appendices

12.1 Design References

• Bangladesh National Building Code (BNBC) 2020, Ministry of Housing and Public Works

• International Plumbing Code (IPC) 2021, International Code Council

• International Mechanical Code (IMC) 2021, International Code Council

• ASHRAE Standard 90.1-2019, Energy Standard for Buildings Except Low-Rise Residential

• ASHRAE Handbook – HVAC Applications, 2019 Edition, Chapter 50: Plumbing

• NFPA 54: National Fuel Gas Code, 2021 Edition

• NFPA 13: Standard for the Installation of Sprinkler Systems, 2022 Edition

• WHO Guidelines for Drinking-Water Quality, 4th Edition, 2017

• AWWA C651-14: Disinfecting Water Mains

• NSF/ANSI 55: Ultraviolet Microbiological Water Treatment Systems

• LEED v4.1 BD+C: Water Efficiency Credit Requirements

12.2 Appendices

The following appendices are attached to this report:

AppendixContent
AFixture Unit Count Worksheets – All Floors
BPipe Sizing Calculations – Water Supply and Drainage
CGas Load Calculations and Pipe Sizing Tables
DRainwater Harvesting Yield and Demand Analysis
EEquipment Data Sheets and Submittals
FWater Quality Test Protocol
GCommissioning Forms and Checklists

— END OF REPORT —

Prepared by: M. Ahmed, PE | Civil & Environmental Engineer | March 2025

Confidential | For Construction Use Only​Page

Comments

    Please login to post comment. Login